Vise Energy Services has a reputation for quality of work, being on budget, and completing projects on schedule. We are privileged to be backed by a dedicated and strong workforce which has allowed us to successfully complete a wide range of projects throughout Western Canada and we are extremely proud to share some of those projects we have been involved with.
Detailed Project History
ALTA-GAS (COMPLETED AT HARMATTAN GAS PLANT) - 2 COMPRESSORS INSTALLED
- Install two new 600HP screw compressors
- Fabricate and install 2900 diameter Inches of 1” to 12” pipe
- Procure all structural for project
- Stress Relief piping both in shop and in field
- Fabricate and install approx. all platform and stairs
- Field tie ins and prep for spring shut down
- Fabrication of stairs, platforms
- 5 and 2 shift over two month period
- Manpower: 10 man crew field / 10 man crew shop
- Code: B31.3
Alta-Gas - Harmattan Gas Plant Compressor Addition
- Purchase and build 100m x 24m high pipe rack within existing facility
- Fabricate and install approx. 30,000 KG structural rack
- Install 1200 horsepower compressors
- Procure all materials and structural for project
- Fabricate approximately 8,000 diameter inches of 1” SOL to 14” skid 80 pipe
- Blast, prime and paint all structural to spec
- Fabricate stairs, platforms and barrel docks for compressors
- Field tie ins and prep for spring shut down
- Man power: 30 man crew
- Code: B31.3
Alta-Gas (Harmattan Gas Plant) - Plant site maintenance and commissioning for new compressor start up
- Build and install operator platforms within existing pipe rack
- Procure all materials and structural for project
- Fabricate tie in spools as needed around site for operations
- Blast, prime and paint all structural to spec
- Build lube oil piping system from existing to new compressors
- Man power: 6 man crew
- Code: B31.3
Alta-Gas (Completed at Sundre Harmattan Plant)
- Install knock out drum and incinerator skids
- Install new structural throughout existing rack
- Fabricate and install all piping for vent lines and fuel gas
- Fabricate and install all piping for drain lines from scrubbers to compressors
- Blast, prime and paint all structural and pipe to spec.
- Man power: 8 Field Install – 6 Shop
- 20 Day construction schedule (5 and 2)
- Code: B31.3
Angle Energy - 7500 BPD Oil Battery
- 6 1000 bbl tank installations
- 5048 inches
- Fabrication of Stairs, Platforms, Tank bases
- Manpower: 18 men staggered, (average 12)
- 59 day work days (24 and 4 schedule)
- Code: B31.3
Project Highlights
- Angle's schedule called for cutting and capping of 80 piles on first day. Vise was able to cut and cap over 200 piles by the completion of first day.
- Due to engineering firm falling behind Vise completed all measurements of pipe by hand in field order for owner to stay on schedule. All measurements were accurate.
APACHE CANADA LTD. (COMPLETED IN ANTE CREEK AREA) - OIL BATTERY
- 10-09 Multiwell pad:
- Six production wells with a 2 phase test separator package
- 3” Flex pipe produced emulsion lines from each well into common ditchline Separator
- 6” group production line to 06-09 battery (.5km)
- 06-09 Oil Battery:
- 4 - 1000 bbl tank installations
- 5900 dia. inches
- Fabrication of Stairs, Platforms
- Internally coated of approx. 35% of all piping
- Tie in to existing single well battery
- Manpower: Field - 16 employees staggered / Shop – 12 employees
- 72 work days between shop and field (24 and 4 schedule)
- Code: B31.3 & Z662
Project Highlights
- Cutting, setting and welding of over 220 piles in the first four days
- Vise completed all measurements and install with P&IDs and basic Navis model only. All measurements were accurate.
ARC Resources - Fabricate Pigging Skid
- Fabricate pigging skid with 2” to 20” Sch.40 piping
- Procure all materials required to complete
- Line up and organize all trades for purposes of tubing trace and insulation
- Manpower: 8 to 10 man shop crew
- 12 Day turnaround to complete
- Code: B31.3 and Z662
Arc Resources Ltd. - Tank Fabrication
- Multiple tank base fabrication 750/1000 BBL
- Both HSS Octagon and Channel formed round bases
- Four CWB certified welders
- Blast, prime and top coat as required
Arc Resources Ltd (Vallyview) - Battery Addition
- 2230 diameter pipe inches
- Fabricate 1” to 6” Sch. 80 pipe
- Fabricate and install piping within existing facility
- Work with ENC coated piping; including procurement and shipping
- Fabrication of stairs, platforms and pipe rack for site
- Manpower: 12 man crew
- 23 Day construction schedule (24 and 4)
- Code: B31.3
ARTIS EXPLORATION (THREE HILLS AREA) - PIPELINE INSTALLATION
- 1.4km-Oil Effluent line 130mm od x 29 wt – Flex pipe FP601
- 3.5km-Natural Gas line 114.0mm od x 3.2mm wt – Steel 359 Cat II
- 3 bores (2 x 100 meters and 1 x 1000 meters)
- Battery upgrade; Demo & fabrication of interconnecting piping 700 dia. Inches
- Well Pad Project; 2 Well Tie In, Inlet Blg. with approx. 1200 dia. Inches
- Worked in conjunction with Completions crews
- 24 and 4 schedule
- B31.3 and CSA Z662
Bellatrix Exploration Ltd. - Multiple Well Pad Projects
- New site construction & refurbishment of old equipment
- Includes a combined 4km of pipeline install
- Manpower: 2 crews / 7-10 men per crew as required
- 24/4 construction schedule
- Code: B31.3 & Z662
Bellatrix Exploration Ltd. - Well Pad Project
- New Well pad project
- New site construction & refurbishment of old equipment; Includes fabrication of pipe supports and piping
- Includes a 1km of pipeline install
- Manpower: 1 crews / 6-8 men as required
- 24/4 construction schedule
- Code: B31.3 & Z662
Birchcliff Energy - Pipeline Installation
- 1km-Fuel gas line 60.3mm od x 3.2mm wt – Steel
- 1km-Fuel gas line 65.0mm od x 7.0mm wt – Fiberspar
- 2km – Sour oil Effluent Line 143.0mm od x 14.0mm Wt – Fiberspar
- 1km – Sour oil Effluent Line 121.0mm od x 13.0mm Wt – Fiberspar
- 3 bores (2 x 500 meters and 1 x 100 meters)
- Code: B31.3 and Z662
Birchcliff Energy - Well Pad Project
- 2 well pad project
- Install separators and tanks
- Manpower: 10 man crew
Connacher Oil & Gas (Algar Facility) - Maintenance
Algar and Pod 1 maintenance
- Tank cleaning
- Pipe and structural installs
- Procure all materials and structural for project
- Fabricate both stainless and carbon replacement spools as needed around site for operations
- Man power: 6 man crew
- Code: B31.3
Connacher Oil & Gas (Mariana Lake - Algar facility) - Maintenance Fabrication and Install
- Fabricate both carbon and stainless spools for shut down
- Twelve day shut down and install – Day and night shifts
- Tank and vessel cleaning
- Man power: 20 Field Install – 6 Shop
- Code: B31.3
CNRL (BILBO FACILITY) - FLARE LINE UPGRADE
- Flare Line Upgrade
- Install new 10’ x 45’ FKOD, 24”x 250’ long flare line and 54”x 190’ flare stack
- Procure all materials and structural for project
- Survey all measurements via Total Station
- Fabricate approx. 3000 dia. inches and tie in spools
- Blast, prime and paint all structural to spec.
- Prime all piping for flare line
- Complete tie ins to existing flare, FKOD, fuel gas
- Man power: 10-man crew
- Shut down complete one day ahead of schedule
- 14 Day construction schedule
- 7 Day shutdown schedule
- Code: B31.3
CNRL (BILBO FACILITY) - SLUG CATCHER UPGRADE
- Slug Catcher Upgrade
- Install new 10’ x 40’ separator
- Procure all materials and structural for project
- Survey all measurements via Total Station
- Build Acorn dwgs and design piping layout
- Fabricate approx. 1100 dia. inches and tie in spools
- Prime all structural and piping
- Complete tie ins to existing slug catcher and pipe rack
- Man power: 8-man crew
- 10 Day construction schedule
- 1 Day shutdown schedule
- Code: B31.3
Ember Resources Ltd. (Stettler Area) - Pipeline and Well-site Installation
- Includes a combined 3.5km pipeline to date
- Over 1100 inches of 2” to 6” piping
- Structural fabrication of stairs, platforms and pipe rack
- Manpower: 10 to 12 man crew as needed
Exoro Energy (Rocky Mountain House and Ponoka Area) - Pipeline and Wellsite Installations
- Multiple separator and battery builds
- Includes a combined 5km pipeline to date
- Over 1500 inches of 2” to 6” piping
- Structural fabrication of stairs, platforms and piperack
- Manpower: 10 to 15 man crew as needed
- Ongoing Schedule
- Code: B31.3 & Z662
Gibsons Energy Ltd. - Pigging Skids
- Pigging Skids (Receiver & Launcher) with 3” to 8” XH piping
- Both 8” and 10” barrels
- Fabricate all structural for skids
- Line u[ and organize all trades for purposes of trace and insulation
- Manpower: 10 to 12 man shop crew
- 8 day turnaround to complete each skid and already within 5 weeks
- Code: B31.3 & Z662
Gibsons Energy (Drayton Valley) - Water Flood Project
- 1900 diameter pipe inches
- Fabricate 1” to 6” Sch. 80 pipe
- Fabricate and install piping within existing facility
- Work with ENC coated piping; including procurement and shipping
- Fabrication of stairs, platforms and pipe rack for site
- Manpower: 14 man crew
- 35 Day construction schedule (24 and 4)
- Code: B31.3
Gibsons Energy (Grande Cache) - Water Flood Project
- 1900 diameter pipe inches
- Fabricate 1” to 6” Sch. 80 pipe
- Fabricate and install piping within existing facility
- Work with ENC coated piping; including procurement and shipping
- Fabrication of stairs, platforms and pipe rack for site
- Manpower: 14 man crew
- 35 Day construction schedule (24 and 4)
- Code: B31.3
Gibsons Energy - Water Flood Project
- 800 diameter pipe inches
- Fabricate 1” to 4” Sch. 80 pipe
- Fabricate and install piping on pump skid
- Install pumps and overhead cranes for skid in Vise Energy yard
- Fabrication of stairs, platforms and pipe rack for site
- Manpower: 8 man crew
- 24 Day construction schedule (24 and 4)
- Code: B31.3
INPLAY OIL (ROCKY MOUNTAIN HOUSE AREA) - WELL PAD PROJECT
- Two well tie in
- Ditch in underground 150m from wells to separator
- Fabricate all piping approx. 380 dia inches
- Fabricate all structural steel
- Threaded off wellhead
- Tie in to existing production line
- Move and set up new separator from existing site
- Fabricate new platforms and stairs for equipment on site
- Manpower 5 to 8 over ten days
- B31.3 and CSA Z662
Keyera Energy Corp - Fabrication
- Fabricate and install 1200 m pipe rack
- Fabricate 1200m of 6” sch 80 pipe
- Fabricate 1200m of 16” sch 80 pipe
- Fabricate 2400m of 8” sch 80 pipe
- Fabrication of stairs, platforms
- Manpower: 30 man crew
- 24/4 Construction Schedule
- Code: B31.3
Keyera Energy Corp - Fabrication
- Fabricate and install tie in spools for the FSPL truck center
- Fabricate 6” and 12” XH pipe for operations
- Fabrication of stairs, platforms
- Manpower: 14 man crew
- 10/4 Construction Schedule Ongoing
- Code: B31.3
Kyoto Fuels - Bio Diesel Plant
- Prime contractor role (Commissioning)
- 66 million Litre Tank Farm installation
- Approximately 15,000 inches
- Manpower: 15 staggered
- 30% stainless
- Code: B31.3
Project Highlights
- Project completed within budget
- No safety incidents for duration of project
As a result of the project quality, cost control, efficiency and the relationship Kyoto Fuels has offered Vise Energy Services the sole construction contracts for their upcoming biodiesel facility making us the prime contractor of the project without going to bid.
Manitok Energy Ltd. - Well Pad Project
- Existing Well pad project
- Refurbishment of old equipment / Well tie in / New pump install; included pump base, supports and pipe fabrication
- Manpower: 1 crew / 4-5 men as required
- 24/4 construction schedule
- Code: B31.3 & Z662
ORLEN UPSTREAM (ROCKY MOUNTAIN HOUSE AREA) - SEPARATOR AND LINE HEATER INSTALL
- Single well tie in
- Install separator and line heater equipment
- Ditch in 2” U/G water line 100m from separator to tanks
- Fabricate all piping approx. 780 diameter inches
- Fabricate all structural steel
- Threaded off equipment
- Install 400m 6” steel line from site to production pipeline
- Tie in to existing production pipeline
- Fabricate new platforms and stairs for equipment on site
- Manpower 10 to 15 over fourteen days
- B31.3 and CSA Z662
Pengrowth Energy - Blending and Condensate Piping Project
- 3000 inches
- Fabricate 2”, 3”, 4” sch 80 pipe
- Fabrication of stairs, platforms and pipe rack
- Manpower: 8 man crew
- 34 day construction schedule (24 and 4)
- Code: 31.3
Pengrowth Energy - Dehy Decommission and Re-Install
- 900 inches
- Fabricate 2”, 3”& 4” Sch. 80 pipe
- Fabrication of stairs, platforms and pipe rack
- Manpower: 7 man crew
- 5/2 construction schedule (Total 24 days to complete)
- Code: B31.3
Pengrowth Energy - Rail Car Loading Rack
- 1000 inches
- Fabricate 3” and 4” sch 80
- Fabrication of stairs, platforms and pipe rack
- Manpower: 8 man crew
- 28 day construction schedule (24 and 4)
- Code: B31.3
PennWest - Battery Upgrades
- Upgraded VRU System
- Installed new boot
- Piping modifications
- 2 phases
- Manpower: 10 men
- 60 day construction schedule (14 and 4)
- Code: B31.3 & Z662
Project Highlights
- No safety incidents
- Job completed on schedule
PERPETUAL ENERGY (MANNVILLE AREA) - 4 WELL TIE IN
- Four well tie in on new Battery site
- Fabricate all piping approx. 2300 diameter inches and all structural steel
- 3” Threaded off wellheads
- Set all equipment and tanks
- Tie into 6 new 1500BBL tanks
- Re utilize existing generator and injection pump equipment
- Move and set up equipment from existing site
- Fabricate new platforms and stairs for equipment on site
- Manpower 14 over 22 days
- B31.3 and CSA Z662
PERPETUAL ENERGY (MANNVILLE) - PIPELINE INSTALLATION
- Install 1.4 km of 97mm Flex Pipe 301 (Oil Emulsion)
- Install 1.4 km of 69mm Flex Pipe 301 (Natural Gas)
- Install 0.80 km of 100mm Flex Cord 901 (Water Injection)
- Cased and bored Alberta County road
- Tie-in and construct 3 well pads
- Includes pile install and all structural
- Approx. 310 dia. Inches plus threading
- Manpower 6 to 10
- Completed in two weeks
- B31.3 and CSA Z662
ROCKPOINT GAS STORAGE (VEGREVILLE) - COMPRESSOR STATION WELL-HEAD TIE IN
- Compressor station well head tie in (Gas storage well)
- Fabricate approx. 500 dia inch carbon steel piping and install
- Fabricate supports for pipe rack to well head and install
- Remove existing DeHy and clean site
- Contract EIC and Insulation services
- Man power: 10 Field Install – 5 Shop
- Code: B31.3
Saguaro Resources Ltd. (Completed in B.C – Pink Mountain Area 2015) - 4 Well Pad Project
- Built under short schedule program
- Fabricate 4,000 Inches of 2” to 8” Sch.80/XXH piping
- Fabricate all structural supports; blast and paint to spec.
- Stress relief of all spools
- Manpower: 14 Field Install
- 24 and 4 construction schedule
- Code: B31.3 and Z662
Saguaro Resources Ltd. (Completed in B.C – Pink Mountain Area 2016) - Phase 1 Plant Expansion
- Built under short schedule program
- Fabricate 4,500 Inches of 2” to 16” Sch.40 to XXH piping
- Fabricate all structural supports; paint to spec.
- Manpower: 24 Field Install
- 24 and 4 construction schedule
- Code: B31.3
Saguaro Resources Ltd. (Completed in B.C – Pink Mountain Area 2016) - 8 Well Pad Project
- Fabricate 5,400 Inches of 2” to 10” Sch.80/XXH piping
- Build and install 10” underground section from existing
- Fabricate all structural supports; paint to spec.
- Stress relief of all spools
- Manpower: 17 Field Install
- 24 and 4 construction schedule
- Code: B31.3 and Z662
Saguaro Resources Ltd. (Completed in B.C – Pink Mountain Area) - Phase 2 Plant Expansion
- Fabricate 5,300 Inches of 2” to 16” Sch.40 to XXH piping
- Fabricate all structural supports; paint to spec.
- Manpower: 20 Field Install
- 24 and 4 construction schedule
- Code: B31.3
Saguaro Resources (Completed in B.C – Pink Mountain Area) - Pipeline Installation
- 10km of 12” heavy wall pipeline.
- Fabrication of pig barrels
- Fabrication of pig catchers
- Fabrication of crossover spooling and interconnecting piping
- Hydrotesting
- Sand blast and coating.
Saguaro Resources (Completed in B.C – Pink Mountain Area) - Well Pad Project
- C78 Well Pad Project
- 5 Well Tie In
- Approx. 3200 dia. Inches
- Worked in conjunction with Completions crews
- 24 and 4 schedule
- B31.3 and CSA Z662
TIMBERROCK ENERGY CORP. (SUNDRE AREA) - PIPELINE, BATTERY AND WELL PAD PROJECT
- 0.7km-Natural Gas line 168.0mm – Steel 359 Cat II
- 0.1km-Emulsion line to tank farm 89mm – Steel 359 Cat II
- 1 bore 80m County Road
- Battery & Well Pad Project;
- All pilings and structural supports
- All stairs and platforms
- 1 Well Tie In 1500 ANSI
- 1 -3 Phase Separator 600 ANSI and 3 Temp. Separators
- 4 -1000 BBL tanks
- Approx. 830 dia. Inches plus threading
- Manpower 10 to 14
- Completed in under two weeks
- B31.3 and CSA Z662
TIMBERROCK ENERGY CORP. (SUNDRE AREA) - PIPELINE, BATTERY AND WELL PAD PROJECT
- 1.6km-Natural Gas line 114.0mm – Steel 359 Cat II
- 2.1km-Natural Gas line 114.0mm – Steel 359 Cat II
- 0.1km-Emulsion line to tank farm 89mm – Steel 359 CatII
- 2 bores (120m and 90m)
- Battery & Well Pad Project;
- All pilings and structural supports
- All stairs and platforms
- 3 Well Tie In 1500 ANSI
- 3 -3 Phase Separators 600 ANSI
- 3 -1000 BBL water tanks
- Existing plant site site header and tie ins
- Approx. 2410 dia. Inches plus threading
- Manpower 14 to 22 – Completed in just over 3 weeks
- B31.3 and CSA Z662
TIMBERROCK ENERGY CORP. (SUNDRE AREA) - PIPELINE, BATTERY AND WELL PAD PROJECT
- 3.2km-Natural Gas line 168.0mm – Steel 359 Cat II
- 0.1km-Emulsion line to tank farm 89mm – Steel 359 CatII
- 3 bores (160m, 50m and 95m including County road)
- Battery & Well Pad Project;
- All pilings and structural supports
- All stairs and platforms
- 1 Well Tie In 1500 ANSI
- 1 -3 Phase Separators 600 ANSI
- 3 -1000 BBL water and oil tanks
- Approx. 690 dia. Inches plus threading
- Manpower 14 to 20 (Manned up to complete quicker)
- Completed in just over two weeks
- B31.3 and CSA Z662
TIMBERROCK ENERGY CORP. (SUNDRE AREA) - PIPELINE, BATTERY AND WELL PAD PROJECT
- 3.3km-Natural Gas line 168.0mm – Steel 359 Cat II
- 1 bores (110m bore County road)
- Battery & Well Pad Project;
- All pilings and structural supports
- All stairs and platforms
- 1 Well Tie In 1500 ANSI
- 1 -3 Phase Separators 600 ANSI
- 3 -1000 BBL water and oil tanks
- Approx. 720 dia. Inches plus threading
- Manpower 15 to 22 (Manned up to complete quicker)
- Completed in just over two weeks
- B31.3 and CSA Z662
Tourmaline Oil Corp. - Fabrication
- Fabricate 14,000 Inches of 2” to 8” Sch.40/XH piping
- Fabricate all structural supports; blast and paint to spec.
- Manpower: 20 Shop Fabrication / 18 Field Install
- 24/4 construction Schedule
- Code: B31.3 and Z662
Tourmaline Oil Corp. - Fabrication
- Fabricate on skid with 2” to 12” Sch.80 piping
- Procure all materials required to complete
- Line up and organize all trades for purposes of NDE, heat trace and insulation
- Manpower: 6 to 8 man shop crew
- 9 Day turnaround to complete
- Code: B31.3 and Z662
Tourmaline Oil Corp. - Fabrication of Camel Back Risers
- Fabricate seven camel back riser skids with 3” to 8” XH and XXH piping
- Fabricate all structural for skids
- Procure all materials required to complete
- Total of 14,000 inches between all skids
- Line up and organize all trades for purposes of trace and insulation
- Manpower: 20 - 25 man shop crew
- Ongoing Schedule; Three month time frame to complete
- Code: B31.3 and Z662
Tourmaline Oil Corp.- Pump Building Install
- Pump building install
- Cut and Cap Piles
- Set building
- Tie in building to existing rack
Whitecap Resources - Pipeline Installation
- Pipeline installation
- 1 km of 3” steel pipe
- 1 bore
- Code: B31.3 and CSZ622
- Manpower: 8 man crew
Yangarra Resources Ltd. - Multiple Separator and Battery Builds
- Includes a combined 10 km pipeline
- Over 4000 inches of 2” to 6” piping
- Structural fabrication of stairs, platforms and piperack
- Manpower: 6-10 man crew as needed
- 150 day construction schedule (24 and 4) as required
- Code: B31.3 & Z662